1. [单选] 在一次风险管理会议上,大多数项目团队成员使用计算机对定量风险分析模型进行了多次迭代。将会有一个累积概率分布(S形曲线)代表达成任何特定结果的概率。项目经理应该使用哪种方法来评估和管理项目风险?During a risk management meeting, most of the project team members use a computer to iterate the quantitative risk analysis model numerous times. There will be a cumulative probability distribution (S-curve) representing the probability of achieving any particular outcome. Which method should the project manager use to assess and manage project risks? A:影响图。Influence diagrams. B:敏感性分析。Sensitivity analysis. C:决策树分析。Decision tree analysis. D:蒙特卡洛分析。Monte Carlo analysis. 2. [单选] 项目经理在执行项目合同过程中收到一项重大差异,项目经理应该进行什么工作来应对额外的工作?The project manager has received a major discrepancy in the execution of the project contract. What should the project manager do to cope with the additional work? A:更新工作分解结构。Update the work breakdown structure. B:更新风险登记册。Updating the risk register. C:更新资源管理计划。Update the resource management plan. D:更新采购管理计划。Update the purchasing management...