Frequently Mis answered Questions on the PMP Exam(5 Qs, Answers Below)-PMPSIM518
1.[单选] 项目经理被指派交付某组织旗舰产品的一个关键解决方案。重要的成功因素包括敏捷性、市场适应能力和对市场上产品/服务的快速响应能力,为了确保公司取得成功,项目经理应该采取的其中一项关键活动是什么?A project manager has been selected to deliver one of an organization's key flagship solutions. Critical success factors include agility market adaptation, and a quick response to market offerings. What is one of the key activities that the project manager should undertake to ensure company success?
2. [单选] 项目经理正在领导一个项目,该项目的几位干系人来自公司其他职能部门,其中一位干系人刚刚晋升为另一个职能部门的负责人,该部门也是该项目的一个干系人,项目经理应该让项目团队更新哪些内容来确保与干系人保持适当沟通?A project manager is leading a project with several stakeholders in other functional areas of the company. One of these stakeholders has just been promoted to lead another functional area, and remains a stakeholder for this project. What should the project manager have the project team update to ensure proper communications to stakeholders?
3.[单选] 项目经理签订了一份合同,领导一个供应商团队,执行全国性的系统实施项目。项目启动后,合同签订组织宣布对系统进行变更,因为另一个独立供应商团队完成了额外工作,这导致合同发生变化,项目经理应如何处理这些变化?
A project manager signs a contract to lead a team of vendors for a nationwide system implementation project. After initiation, the contracting organization announces changes to the system, as additional work was completed by another team of independent vendor this resulted in variations to the contract. How should the project manager deal with these changes?
4.[单选] 项目经理如何制定项目管理计划,以确保项目持续交付预期效益?How should the project manager develop the project management plan to ensure that the project continually delivers the expected benefits?
5.[单选] 项目经理刚刚开始管理敏捷项目。项目经理意识到,由于缺乏对项目目标和“定义已完成”(DoD)的清晰定义,其同事的多个项目遇到很多困难。发起人不断要求交付更多功能,项目尚未完成。项目经理应采取什么措施来避免发生这些问题?A project manager just started managing agile projects. The project manager realizes that due to the lack of a clear definition of project objectives and definition of done (DoD), their colleague's projects have had many difficulties. Sponsors keep asking for more features and the projects have yet to be completed. What should the project manager do to avoid these issues?
1.A
ReplyDelete2.B
3.D
4.D
5.D
1.解析:敏捷实践指南,5.1-项目章程和团队章程,P49。题干强调了项目的成功要素包括敏捷性,但是敏捷项目也至少需要有项目愿景或目标,因此项目经理应该和发起人共同审查下项目目标,并优先关注当前可以明确实现的成果。选项B和C都应该在A之后,选项D,应该先执行A,再判断是否需要修改项目可交付物以及重新界定目标
Delete2.解析:过程组:实践指南,P206,沟通管理计划。一道很让同学们纠结的题目,沟通是参与项目的人员之间的信息流动和调动干系人参与项目的方式之一,所以似乎选择干系人登记册和干系人参与计划也说的通。但是,要注意因为项目的系统属性,在对项目进行管理时,面对一个问题可能存在多个驱动因素,但是会存在一个因素是最为重要的。回到情景,确保与干系人的适度沟通,显然最不能缺少的因素就是沟通管理计划,如果缺失,将出现沟通上的混乱,因此B选项正确。选项A,沟通管理计划虽然包含在项目管理计划中,但是我们要选最为精准的。选项CD,会影响沟通的效果,但不是最为关键的因素,排除。
3.解析:过程组:实践指南,P78,5.1- 制定项目管理计划。项目经理签了合同,拿了个活,结果刚准备做,被组织的其他团队完成了一部分了,所以要更改合同范围。为了应对这种变化,项目经理应先做好支持变更以及上报的计划。 其他选项:A,直接开具发票不符合流程;B,已经有了变更不能按初始合同来做;C,合同变更阶段,还没有到具体的供应商工作执行。
4.解析:
为确保项目持续交付预期效益,项目经理应在计划中明确每个工作产品的目标,从而:
对齐战略价值:将可交付物与商业论证中的效益直接关联(如“模块X目标:减少20%用户操作步骤”)。
动态监控:通过目标达成度评估效益实现情况,及时调整执行策略。
其他选项分析:
A(集成测试):是质量保障活动,非效益管理核心。
B(全员测试):聚焦技术验证,忽略商业目标。
C(澄清效益):是启动阶段任务,非计划制定内容。
知识点对应:
《PMBOK指南》(第6版)第1.2.6节:效益管理计划需分解到可交付物层级(第31页)。《商业分析实践指南》:工作产品目标需映射至业务价值(第87页)。
5.解析:因为没有与干系人的共同认同的目标的定义,所以产生的一系列的问题,如果在最初都明确的章程和期望就能避免这一问题的产生,故D选项是比较合适的。缺乏对项目目标和“定义已完成”(DoD)的清晰定义——项目章程。