Frequently Mis answered Questions on the PMP Exam(5 Qs, Answers Below)-PMPSIM506

 1. [单选] 一个客户支持团队已经为处理客户报告的问题制定了短周期的迭代工作计划。最近,出现了一大批高优先级的问题,打乱了最初的计划,团队经理发现很难管理进展。项目经理应建议使用哪种方法?A customer support team has planned short, iterative cycles for working on customer-reported issues. Recently, there was a surge of high-priority issues that disrupted the original plan, and the team's manager is finding it difficult to manage the progress. Which approach should the project manager suggest using?

  • A:敏捷Scrum方法。Agile Scrum approach.
  • B:螺旋方法。Spiral approach.
  • C:敏捷看板方法。Agile Kanban approach.
  • D:快速应用开发方法。Rapid application development approach.

  • 2. [单选] 项目经理正在参与一个项目,是将办公地址从一个建筑迁移到另一个建筑,项目经理想要与干系人共享项目状态。应该采用哪种方式?The project manager is involved in a project to relocate the office from one building to another. To share the project status with stakeholders, which method should the project manager adopt?
    • A:正式和口头沟通Formal and oral communication
    • B:正式和书面Formal and written
    • C:非正式和书面Informal and written
    • D:非正式和口头Informal and oral

    • 3.  [单选] 一个项目经理正在领导一个涉及70个干系人的大型项目,项目经理从客户那里听到了各种意见和期望,其中一些是相互矛盾的。因此,一些需求不清楚。项目经理应该做什么来建立关于需求的共识?A project manager is leading a large-scale project that involves 70 stakeholders. The project manager has heard various comments and expectations from the customers, some of which are contradictory. Consequently, some requirements are not clear. What should the project manager do to build consensus regarding the requirements?
      • A:把这个上报给管理团队,让他们审查和指导。Escalate the issue to the management team for their review and guidance.
      • B:创建一个调查模板,收集干系人的反馈,以达成协议。Create a survey template to collect feedback from stakeholders to reach an agreement.
      • C:组织一次与所有干系人面对面的会议,了解他们的利益和关注点。Organize a face-to-face meeting with all stakeholders to understand their interests and concerns.
      • D:利用专家的判断来确定应该考虑的要求。Leverage expert judgment to determine the requirements that should be considered.

      4. [单选] 在给项目团队分配任务后,项目经理发现一些团队成员感到不舒服。相同的团队成员在理解分配给他们的任务时遇到困难,而其他团队成员则在挑战基于项目分配的时间表。塔克曼阶梯理论的哪个阶段正在发生?After assigning tasks to a project team, a project manager discovers that some team members are uncomfortable. Same team members are having difficult time understanding their assigned tasks, whereas other team members are challenging the schedule based on that allocation to the project. Which phase of the Tuckman ladder of team formation is occurring?
      • A:形成阶段。Forming.
      • B:成熟阶段。Mourning.
      • C:震荡阶段。Storming.
      • D:规范阶段。Forming.

      • 5. [单选] 项目团队已经识别出一个风险,并希望将其作为一个机会来比计划更早完成项目。项目经理意识到,由于发起人对风险的厌恶,可能不会接受这个风险。项目经理应该怎么做?A project team has identified a risk and wants to accept it as an opportunity to finish a project earlier than planned. The project manager realizes that the sponsor may not accept the risk since the sponsor is risk averse. What should the project manager do?
        • A:创建一个应急储备来覆盖风险,以确保风险会被接受。Create a contingency reserve to cover the risk in order to ensure that the risk will be accepted.
        • B:进行蒙特卡洛分析,以确定团队是否会提前完成项目。Conduct a Monte Carlo analysis to determine if the team will complete the project early.
        • C:向发起人解释,这是一种无事件类型的风险,接受它是没问题的。Explain to the sponsor that this is a nonevent type of risk and it will be fine to accept it.
        • D:说服发起人,这将会减少成本,最终为发起人带来更多的利润。Convince the sponsor that this will cost less, ultimately resulting in more profit for the sponsor.

Comments

  1. Replies
    1. 1. 解析:敏捷实践指南,A3.4-看板方法,P103。选C,对于这种情况,最佳方法是敏捷看板,它使用可视化看板来管理工作流程并限制在制品。看板帮助项目经理和团队对最重要的问题进行优先排序,监视每个问题的状态和进展,并优化向客户交付价值的过程,看板适用于具有频繁和不可预测变化以及高度变异和不确定性的项目。选项A,Scrum适用于需求优先级明确以及每个冲刺内变化最小的项目。Scrum通常在规划会议上设置优先级,而在冲刺期间不鼓励进行大的优先级更改,而看板允许随时调整任务的优先级,非常适合于优先级经常变化的环境。选项B错误,螺旋是一种结合了瀑布和原型设计元素的方法,使用规划、风险分析、工程和评估的循环过程。螺旋适用于具有复杂和高风险需求、以及需要广泛测试和验证的项目。选项D错误,快速应用开发方法(RAD)是一种使用快速原型和用户反馈在短时间内交付产品功能组件的方法。RAD话用于具有明确定义和模块化需求、以及有用户参与和协作的项目。

      2. 解析:正式沟通提供了明确、结构和可记录的信息。书面沟通确保所有干系人都能收到相同的信息,并且这些信息可以被引用或存档。对于办公迁移这样的项目,正式和书面的沟通方式可以确保信息的准确性、一致性和可追溯性。B选项最佳。

      3. 解析:C是最佳选项,在需求不清晰、或存在相互矛盾的情况下,项目经理应该组织一个面对面的会议,直接与所有的干系人沟通,以了解他们的需求、兴趣和关注点,这样可以帮助项目经理更好地理解各方的需求和期望,从而更好地管理这些需求,并尽可能地解决相互之间的矛盾。选项B不是最佳选项,创建调查模板虽然可能对收集反馈有所帮助,但这种方法无法解决需求之间的矛盾,并且面对面的会议可以提供更多的信息和理解。

      4. 解析:形成阶段:在本阶段,团队成员相互认识,并了解项目情况及他们在项目中的正式角色与职责。在这一阶段,团队成员倾向于相互独立,不一定开诚布公。震荡阶段:在本阶段,团队开始从事项目工作、明白如何共事时,可能会出现一些冲突或斗争。规范阶段:在规范阶段,团队成员开始协同工作,并调整各自的工作习惯和行为来支持团队,团队成员会学习相互信任。成熟阶段:进入这一阶段后,团队就像一个组织有序的单位那样工作,团队成员之间相互依靠,平稳高效地解决问题。解散阶段:在解散阶段,团队完成所有工作,团队成员离开项目。通常在项目可交付物完成之后,或者在结束项目或阶段过程中释放人员,解散团队。选C。

      5. 解析:蒙特卡洛分析是一种定量风险分析技术,它能够通过模拟项目的不同结果来评估风险和机会,从而提供更具说服力的数据支持风险接受的决策。进行蒙特卡洛分析可以帮助项目经理和团队以及发起人了解接受这个风险带来的机会(提前完成项目)的可能性,答案选B。